Canadian business news: the Darlington SMR has slipped: Ontario Power Generation admitted on November 10 that the first small modular reactor at Darlington will not hit its October 2030 target or stay inside its 7.7 billion dollar budget.
By Maplestime Business Desk | Toronto, Ontario | November 15, 2026
Sources: Power Engineering, World Nuclear News, Nuclear Engineering International | Last updated: November 15, 2026
Quick Answer: The Darlington SMR project will miss its October 2030 target and its 7.7 billion dollar budget, Ontario Power Generation admitted in its third quarter report on November 10. No new date or cost has been given. Construction continues, and a full cost and schedule review is due by mid 2027.
Key Takeaways
- OPG said Unit 1 of the Darlington New Nuclear Project is “no longer expected to achieve the previously disclosed commercial operation date target of October 2030 or be completed within the previously disclosed estimated cost of CAD 7.7 billion.”
- OPG has spent 2.86 billion dollars through September 30, about 37 per cent of the budget, with no revised cost estimate or completion date given.
- The total budget for all four BWRX-300 units is 20.9 billion dollars, approved by Ontario in May 2025.
- OPG blamed ongoing engineering by reactor designer GE Vernova Hitachi Nuclear Energy on its first of its kind BWRX-300 design, which is affecting construction and the supply chain.
- A comprehensive cost and schedule reassessment is expected to be substantially complete by mid 2027.
Why Did the Darlington SMR Fall Behind?
This is a first of its kind problem, literally. OPG attributed the overrun to ongoing engineering by GE Vernova Hitachi Nuclear Energy on its first of its kind BWRX-300 design, which is affecting construction execution and supply chain performance.
To be clear, this is new news. This November 10 cost and schedule warning is a different development from the November 6 announcement of 14 supply contracts for the project, which Maplestime already covered. The contracts were good news. This is the bill coming due on a reactor design that has never been built before.
OPG will now carry out a comprehensive cost and schedule reassessment, expected to be substantially complete by mid 2027. Until then, nobody knows the new date or the new price tag.
What Does This Cost Ontario Ratepayers?
The numbers are already large. The 7.7 billion dollar estimate covers Unit 1 plus systems and services shared with the other planned units, with 6.1 billion dollars allocated to Unit 1 itself. The total budget for all four units is 20.9 billion dollars. OPG has spent 2.86 billion dollars through September 30, about 37 per cent of the budget.
On November 10, OPG also amended its pending Ontario Energy Board application for electricity rates from 2027 to 2031 and withdrew most of the requested approvals for the Darlington SMR facilities, including forecasts for capital additions to its regulated asset base, financing costs and electricity production. That is a significant step back from asking ratepayers to fund the project on the old numbers.
Public money already committed includes a combined 3 billion dollar equity commitment from the Canada Growth Fund and the provincial Building Ontario Fund.

Is Construction Still Going Ahead?
Yes. OPG President and CEO Nicolle Butcher said: “We have made meaningful progress in building the G7’s first small modular reactor, and critical work continues every day on site. At the same time, we have identified risks that will impact Unit 1’s schedule and budget.”
The progress is real. OPG has installed a 2.1 million pound basemat, the first nuclear foundation laid in Canada in more than 30 years, completed the first turbine building foundation pour, and finished assembling a tunnel boring machine. Tunnelling is expected to begin in the fourth quarter of 2026.
So the project is not cancelled. It is late, it is over budget by an unknown amount, and Ontario will not know the real numbers until mid 2027. For a project sold as the future of clean power in this province, that is a long time to wait for an honest price.
Frequently Asked Questions
When will the first Darlington SMR now be finished?
OPG has not given a new date. The October 2030 target is off the table. A full reassessment is due by mid 2027.
How much will it cost now?
Unknown. The 7.7 billion dollar estimate for Unit 1 no longer holds, and OPG has given no revised figure. The total budget for all four units was 20.9 billion dollars.
Is this the same story as the November 6 supply contracts?
No. The November 6 announcement covered 14 supply contracts for the project. This is the separate November 10 third quarter warning that the first unit will miss its 2030 target and its budget.
Maplestime will provide updates from the Darlington SMR project as announcements are made.
Have a tip about the Darlington SMR project? Email [email protected]
Have a correction? Email [email protected]
Do you think Ontario should keep pouring money into a first of its kind reactor, or cut its losses and spend the cash on power we can build faster? Tell us in the comments. And share this with every Ontarian watching their hydro bill.