Winnipeg city news: Winnipeg could run out of sewage treatment capacity as much as a year before the upgrades meant to fix it are finished, according to a new report to city council.
By Maplestime Winnipeg Desk | Winnipeg, Manitoba | November 24, 2026
Sources: CBC News | City of Winnipeg | Last updated: November 24, 2026
Key Takeaways
- Winnipeg’s three sewage treatment plants can handle all expected residential and industrial wastewater only until late 2029, under the worst case in the report.
- The new biosolids facility at the North End Water Pollution Control Centre is not due until the final three months of 2030, leaving a possible one year gap.
- The crunch happens only if Winnipeg grows faster than expected, or if new water heavy industries start operating in the city.
- The city has room right now for 25,000 to 35,000 more people, its expected growth by the end of 2029.
- The new headworks, which screens out rags, dirt and sand, may buy enough capacity to bridge the gap.
- The final nutrient removal phase is due in 2032 and should add two more decades of treatment capacity.
- All three levels of government have committed funding to the $3.2 billion project.
The One Year Gap
A report to city council, published Tuesday, November 24, 2026, lays out the worst case from the city’s water and waste engineers. The three plants can process all existing and expected wastewater until late 2029. The biosolids facility that converts partly treated sludge from all three plants into biosolids is not expected to be finished until the final three months of 2030. That is the gap. It only bites if growth beats expectations, or if new industrial businesses that use a tremendous amount of water begin operating in Winnipeg.
What the City Says
Winnipeg water and waste director Tim Shanks told CBC News the timing will be tight. Quote: “Those brand new digesters, it’s going to be pretty close.” He added: “We’re on schedule, on budget and feel pretty good about that project right now. But we’re not going to hang our hat on that alone. We are working on some other contingencies in case there’s a gap there between the finishing of that project.”
Water and waste engineering manager Cynthia Wiebe wrote in the report that the city has enough capacity to handle sewage for another 25,000 to 35,000 people, the expected growth by the end of 2029. She also said the first phase headworks might improve capacity long enough for the biosolids facility to come online the next year.
The Three Phases of the North End Upgrade
The North End Water Pollution Control Centre is more than 90 years old. It treats about 70 percent of Winnipeg’s wastewater and 100 percent of the solids removed at all three of the city’s treatment plants. The upgrade is the largest capital project in Winnipeg’s history, at more than $3 billion, and it is being built in three phases while the plant keeps operating.
- Project 1, Power Supply and Headworks Facilities: a new power substation and systems to pump and screen incoming wastewater. The new headworks began operating in August 2026, and the project is expected to be complete in 2027. Budget $565 million.
- Project 2, Biosolids Facilities: will handle sludge from all three city plants and process it into biosolids. Construction began in August 2026. Sludge treatment is expected to start in October 2030, with overall completion in 2031.
- Project 3, Nutrient Removal Facilities: will treat the liquid part of wastewater before it enters the river and cut the nutrients released into waterways. Expected completion in 2032. Budget $1.57 billion. The federal government committed $500 million on October 30, 2026, with the city and province paying $500 million each.
Why This Project Started in 2003
The project was originally envisioned in 2003, the year after a major sewage spill at the North End plant sparked a provincial order to improve sewage treatment at all three city plants.

Maplestime will provide updates from Winnipeg’s sewage treatment capacity as announcements are made.
Have a tip about Winnipeg’s sewage treatment capacity? Email [email protected]
Have a correction? Email [email protected]
Do you think Winnipeg will close the one year gap before 2030, or is this another deadline the city will miss? Tell us in the comments. And share this with every Winnipegger following the $3.2 billion North End upgrade.