Winnipeg news: The Kenaston Boulevard Widening now carries a $757 million price tag, more than four times what the city estimated in 2009, and Mayor Scott Gillingham wants it to be the defining project of this term even though neither senior government has promised a dollar toward it yet.
The Kenaston Boulevard Widening is pegged at $757 million, more than four times the $129 million estimate from 2009. It would widen Kenaston to three lanes between Taylor and Ness, rebuild the St. James bridges and separate storm and sanitary sewers. Mayor Scott Gillingham wants work started this term, but neither Ottawa nor the province has committed funding yet.
By Maplestime Winnipeg Desk | Winnipeg, Manitoba | November 16, 2026
Sources: Winnipeg Free Press, Coun. Emma Durand-Wood | Last updated: November 16, 2026
Key Takeaways
- The Kenaston Boulevard Widening is now estimated at $757 million: $613.9 million in construction costs plus $143.4 million in financing.
- The cost has risen more than fourfold since the $129 million estimate in 2009, and about 102 percent since the $375 million estimate in 2015, while cumulative inflation since 2015 is 33.75 percent.
- The project would widen Kenaston and Route 90 to three lanes each way between Taylor and Ness avenues, rebuild the St. James bridges, separate storm and sanitary sewers, and add active transportation paths.
- Mayor Scott Gillingham wants construction started before the next election, but neither the federal nor the provincial government has committed funding yet.
What Is Behind the Kenaston Boulevard Widening Price Tag?
This story is based on a Winnipeg Free Press column published today, November 16, on Mayor Scott Gillingham’s plan to make widening Kenaston Boulevard, Route 90, his top infrastructure priority this term. The cost figures below come from that column and from Coun. Emma Durand-Wood’s primer on the project, not from a new city announcement.
The price history reads like a warning. The project was estimated at $129 million in 2009, then $375 million in 2015 and $450 million in 2018. By 2019 the city was ballparking about $500 million. A 2023 Class 3 estimate, meaning costs were considered accurate within plus or minus 20 to 30 percent, came in at $736.7 million in combined construction and financing costs. The current estimate is $757 million.
The column puts those numbers against inflation, and the gap is the story. “The cumulative increase in inflation in Canada since 2009 has been 44.54 per cent. The cumulative rise in the cost of the Kenaston project is much, much more,” the column says. Compared with the 2015 estimate of $375 million, the cost has risen about 102 percent, while inflation has grown 33.75 percent since 2015.
What Would the Project Actually Build?
The scope goes well beyond extra lanes. The project would widen Kenaston and Route 90 to three lanes each way between Taylor and Ness avenues, rebuild the St. James bridges, separate storm and sanitary sewers, and add active transportation paths.
The sewer work matters on its own. “The project is not without clear merits: decoupling storm sewers and sanitary sewers is a pollution-control measure that has to be undertaken,” the column says. Improving traffic flow and active transportation also have real value. The question the column raises is not whether the work is worth doing, but at what cost, and who pays.

Who Pays, and What If the Price Keeps Climbing?
Gillingham wants construction started before the next election, and the city has been clear that it wants federal and provincial involvement. But neither higher level of government has said it will play ball, and that leaves the funding question dangling.
Winnipeg has recent reason to worry about big project estimates. The North End sewage treatment plant was estimated at $1.8 billion in 2019 under a Class 3 estimate, and now costs about $3.1 billion, well over the proposed 30 percent maximum variance. Federal and provincial governments have committed a combined $1 billion to finish it, after the city threatened taxpayers with massive water and sewer increases.
Coun. Durand-Wood’s primer puts the Class 3 range for Kenaston at $491.1 million to $798.1 million, and notes that just the widening component could cost the city about $8.5 million a year for 30 years in debt service, over $255 million in total, even with other governments’ help. If Kenaston follows the same pattern as the sewage plant, the $757 million figure may not be the final number Winnipeggers see.
Frequently Asked Questions
What is the current cost of the Kenaston Boulevard Widening?
The current estimate is $757 million: $613.9 million in construction costs plus $143.4 million in financing.
What would the project build?
It would widen Kenaston and Route 90 to three lanes each way between Taylor and Ness avenues, rebuild the St. James bridges, separate storm and sanitary sewers, and add active transportation paths.
Has funding been committed?
No. The city wants federal and provincial involvement, but neither government has committed funding yet.
Maplestime will provide updates from the Kenaston Boulevard Widening as announcements are made.
Have a tip about Kenaston Boulevard or Winnipeg infrastructure? Email [email protected]
Have a correction? Email [email protected]
Do you think widening Kenaston is worth $757 million, or is this another Winnipeg megaproject that will cost far more than promised? Tell us in the comments. And share this with every Winnipegger who drives Route 90.
Enjoying Maplestime? Support independent Canadian journalism — no paywall, no corporate owners.